From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.Calls for an official inquiry into the financial evidence used to justify the construction a £1.34bn nuclear fuel plant at Sellafield in Cumbria will be treated seriously, the National Audit Office has told The Independent.
Michael Meacher, an environment minister in the previous Labour government, who reluctantly gave the go-ahead for the uranium-plutonium mixed oxide (Mox) plant to be licensed in 2001, said he intends to write to the Audit Office demanding an investigation into the evidence that led to the decision.
A spokesman for the National Audit Office said the Sellafield Mox Plant, which has cost more than the 2012 Olympic Stadium to build and a further £800m in commissioning and operating costs, is not on its programme of inquiries, but that the office would give Mr Meacher's request "serious consideration".
A heavily redacted report by the management consultancy Arthur D Little, prepared at the time when the licence was being considered, claimed that the Sellafield Mox Plant would earn about £150m in foreign revenue over its lifetime by fabricating Mox fuel for mostly Japanese nuclear power companies.
However, nearly 10 years after the plant was licensed to operate, it has produced only 13.8 tonnes of Mox fuel, instead of the stated target of 120 tonnes a year. None of the fuel that has been made is destined for Japan, which was supposed to become the main market for Mox.
Despite the failures, the Mox plant at Sellafield is due to be kept open at least until the end of the decade, at a cost to the British taxpayer of nearly £90m a year. The Nuclear Decommissioning Authority, which runs the Sellafield site, said that the first shipment of Mox fuel to Japan will not take place until the end of the decade.
However, the nuclear crisis in Japan has cast a shadow over even this extended delay in the schedule. Some commentators now doubt whether the plant will ship any Mox at all to Japan, contrary to evidence presented to the government when it was licensed in 2001 – five years after the plant was built during the previous Conservative government.