New waste plant to cost BNFL pounds 100m

Susan Watts
Friday 03 June 1994 18:02 EDT
Comments

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

BRITISH Nuclear Fuels is to spend at least pounds 100m on a new facility to handle highly radioactive waste from its Sellafield reprocessing plants, just three years after opening a pounds 240m installation to deal with the waste, writes Susan Watts.

The new plant will operate alongside two existing vitrification lines that convert high-level waste from the liquid form that emerges after reprocessing into glass blocks for long-term storage and disposal.

In its announcement of the new line on Thursday, BNFL admitted it had had 'teething problems' with its two existing vitrification lines. These have been working at less than half their target capacity and with a history of safety problems.

Melters used during the vitrification process were not able to withstand the thermal shock of glass being poured through them, BNFL said, and had to be replaced more often than expected. Other equipment associated with the melters wore out more quickly as a result.

The company had anticipated that production would reach 600 blocks a year. However, early runs produced just 113 blocks a year, rising to 267 last year, BNFL said. Melters on the new line will have an extra jacket on the outside to avoid this problem, and the company hopes the three lines will be producing 600 blocks a year by 2000.

The new line will help cope with the backlog and with extra waste generated once BNFL's controversial new pounds 2.8bn Thermal Oxide Reprocessing Plant (Thorp) starts up. This is not now expected until later this month, after a three-month delay following a spillage at the end of March of highly corrosive nitric acid.

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in