Big Ben: Extra £18m needed for tower repair works, MPs told

Surveys discover asbestos in Elizabeth Tower belfry and extensive use of toxic lead paint

Thursday 13 February 2020 03:15 EST
Comments
2017: Big Ben sounds its last bong before renovation works begin

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

An extra £18.6m is needed to repair the tower which houses Big Ben, parliamentary authorities have been told.

The new costs would see the renovation bill rise by almost a third from £61.1m to £79.7m.

The increase has been put down to the discovery of asbestos, pollution and the discovery of extensive Second World War bomb damage in the Elizabeth Tower, which is home to the capital’s famous bell.

But a spokesman for the House of Commons Commission said members were “extremely disappointed” by the request for “yet more funding”.

“It is very frustrating to learn that the Elizabeth Tower project requires yet more funding, having agreed an extra £32 million in 2017,” he said.

“We have requested more detailed information about the lessons learned from this experience – as well as assurances that more robust estimates are prepared for works of this nature in the future.”

The full scale of the work needed to complete the refurbishment by the late 2021 deadline only became clear when the renovation team began the first ever “intrusive surveys” on the 177-year-old structure, officials said.

The discoveries included asbestos in the belfry, broken glass in the clock dials, extensive use of toxic lead paint and defects in previous work, the House of Commons and House of Lords Commissions were told.

Ian Ailles, director general of the House of Commons, said the works are proving “more complex than we could have anticipated”.

“With a 12m square (130 square feet) footprint and a prime location right in the middle of a busy working Parliament, understanding the full extent of the damage to the Tower was impossible until the scaffolding was up,” he said.

“Alongside other issues, such as the impact of often inappropriate conservation methods used by our predecessors, the corrosive levels of pollution in the atmosphere and the discovery of asbestos in unexpected places, we have only now been able to fully understand the full investment required for this project.”

The new budget will be set if it is approved by the accounting officers of the two houses.

Press Association

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in