Poland, Czech governments close to deal on lignite mine

The Czech government says it has reached a draft agreement with Poland to end months of costly stalemate over a Polish lignite mine that Prague says is harmful to the border area

Via AP news wire
Thursday 03 February 2022 06:10 EST
Poland Czech Mine
Poland Czech Mine (Copyright 2022 The Associated Press. All rights reserved)

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

The Czech government said Thursday it has a draft agreement with Poland to end months of costly stalemate over a Polish lignite mine that Prague says is harmful to the border area environment.

Government spokesman Vaclav Smolka said the government has approved a draft deal about the Turow mine, in southwestern Poland, close to the Czech and German borders.

Czech Prime Minister Petr Fiala told the local CTK news agency he was meeting with his Polish counterpart, Mateusz Morawiecki who is in Prague, and “we’ll be fine tuning the final details.”

Last year Prague took the dispute to The European Court of Justice, arguing that Poland had ignored its protests and the mine was draining water from Czech villages and causing other environmental harm. It ordered Poland to close the colliery pending a decision and imposed a fine of 500,000 euros for each day it continues to operate.

On Thursday, a court official, the advocate general, said that Poland infringed European Union law with a decision to grant the Turow mine a six-year license extension without carrying out an environmental impact study.

The opinion was issued as part of the court's procedure ahead of a verdict, expected later this year.

Poland is refusing to pay the fine and says it cannot close the mine, which supplies a power plant that generates almost 9% of the nation’s energy.

In the legal opinion for the Luxembourg-based European Court of Justice, Advocate General Priit Pikamäe said mining activities carried out “over a surface area similar to that of the Turow mine present, by their nature, a risk of notable environmental effects and must necessarily be subject to an assessment.”

While the European Court of Justice is not bound to follow the advocate general's opinion, it generally does.

The EU earlier this month started the process to deduct millions of euros from payments to Poland in order to cover fines imposed on Warsaw for ignoring the court injunction. The first payment amounts to 15 million euros ($17 million) plus 30,000 euros in interest.

____

Petrequin reported from Brussels. Karel Janicek in Prague contributed.