Paris rushing to finish 2024 Olympics construction work
Paris is rushing to finish construction work in time for the 2024 Olympics with just 18 months to go
Your support helps us to tell the story
From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.Paris is rushing to finish construction work in time for the 2024 Olympics with just 18 months to go.
Delays are being experienced in part because of the impact of Russia's war in Ukraine on the steel industry.
A venue, which was due to be finished this summer, won't be completed until the beginning of next year — only a few months before the Paris Games get underway on July 26, 2024.
The arena at Porte de la Chapelle, a multicultural and working class neighborhood of the French capital, will host badminton and rhythmic gymnastics events. The facilities will also be used at the Paralympics before being handed over to local clubs and schools.
The steel that was going to be used for the arena was initially going to be provided by Ukraine, said Christophe Rosa, the deputy general delegate of the Paris Olympic and Paralympic delegation at Paris City Hall.
Ukraine’s steel producers union said this month that output fell by more than 70% last year because of Russia’s invasion and the destruction of major plants.
“We’ve found solutions to source steel from other places in Europe including in the east, in Poland, but also a number of manufacturing plants in Southern Europe in order to contain delays and aim to finish the works in 2023,” Rosa said on Monday.
The construction work, which costs about 138 million euros ($150 million), requires 1,500 tons of steel.
The place will be called Adidas Arena after a deal reported to be worth around 2.8 million euros ($3 million) per year with the sportswear company was approved by city hall last year.
The arena itself will seat up to 8,000 people for sports events and live performances, and it will become the future home of Paris Basketball club.
Two gymnasiums next to the venue will provide sport facilities that are much needed in one of the poorest areas of the capital, according to Paris City Hall. In recent years, the location had been home to hundreds of migrants and asylum-seekers living in squalid conditions in makeshift camps that have been regularly cleared by police.
During the Paralympics, the facilities will host badminton and weightlifting events, and will later be used by a wheelchair basketball club for practice.
“It’s the only venue that we’re having to build in the city of Paris for the Olympic Games," said Eve Brunelle, equipment project manager at the Paris Olympic and Paralympic delegation at city hall. “We’re renovating many, including training grounds for the Games.”
Other major construction work includes Olympic Village, which will house about 15,000 athletes and officials, and the swimming pool, both located in the suburban area north of Paris.
___