Supply chain issues could slow fix of Florida electric grid

Crews are starting to fix Florida's electric grid by repairing and rebuilding where lines were damaged or flooded by Hurricane Ian

David Koenig
Friday 30 September 2022 19:19 EDT
Tropical Weather Florida
Tropical Weather Florida (© South Florida Sun Sentinel 2022)

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

Crews are beginning to repair — and in some cases, rebuild — Florida's power grid after the state was pummeled by Hurricane Ian.

Florida Power & Light says it stockpiled enough poles, generators and wire to do the work. But power-industry officials warn that kinks in the nation's supply chain could slow the recovery if Ian causes more damage as it spins up the Atlantic coast, or when another natural disaster strikes somewhere else in the U.S.

Eric Silagy, CEO of Florida Power & Light, said that Friday evening 850,000 of the utility's customers who lost power in the storm remained without power, but 1.2 million had power restored during the day.

Ian crossed Florida’s Gulf Coast on Wednesday as one of the strongest storms to ever hit the U.S.

Silagy said earlier this week that the company had set aside enough generators in the months before Ian to complete repairs.

Nationally, however, there is a shortage of distribution transformers that take electricity from high-voltage lines and reduce it to levels that can be used in homes and businesses, industry officials said.

“It's a critical component to the electrical grid that has been in scarce supply for a number of months now,” said Joy Ditto, president and CEO of the American Public Power Association. “We started to recognize it as a national concern in late winter, early spring, and the situation is getting worse.”

It used to take about three months for a transformer to show up after being ordered, but now it is taking more than a year, Ditto said. She said that is limiting the ability of companies to stockpile the boxes, and as a result, they are increasingly swapping boxes with utilities facing a shortage.

There are about a half-dozen U.S. manufacturers of the transformers that are dealing with labor and raw-materials shortages. Ditto said the main choke point is the specialty steel used in transformers — there is only one U.S. manufacturer for that. Her group and the National Rural Electric Cooperative Association asked the Energy Department in May to suspend a 2016 efficiency standard that they say is partly responsible for the steel shortage, but the department has not gone along.

Scott Aaronson, an official at the Edison Electric Institute, which represents for-profit utilities, said the industry is prioritizing supplies during hurricane and wildfire season.

“These efforts help to ensure we are ready to share materials with companies impacted by Hurricane Ian if necessary,” he said by email.

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in