Flagship East Coast line fails to run trains on time

Randeep Ramesh Transport Correspondent
Wednesday 26 March 1997 19:02 EST
Comments

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

Four out of 10 trains on the fastest train line in Britain are not running on time, according to leaked company figures.

Great North Eastern Railway, which runs the high-speed link between London and Edinburgh, has previously trumpeted a 3 per cent improvement in punctuality, but has yet to meet the demanding targets set out in the company's passenger charter.

The railway's internal "Team Brief" document describes the performance as "disappointing" and says that in a "critical period" after Christmas, performance targets were met on just two days.

According to the briefing, passengers waiting for a train on the high- speed line over a four- month period from October last year found that only 62.5 per cent of services ran on time.

But under the passenger charter - which allows season ticketholders to be able to claim refunds for poor performance - GNER is allowed to claim that services within 10 minutes of their arrival or departure time are "on time". Even with the extra leeway, GNER did not meet its charter targets of 90 per cent.

In the two months from December last year, the company managed only 82.8 per cent under the passenger charter - which excludes delays caused by crime, vandalism and poor weather.

However, railway pressure groups said that the "flagship route should be delivering a premium service".

Jonathan Bray, a spokesman for Save Our Railways, said: "This railway benefited from pounds 500m of investment prior to its sell-off. Passengers expect, and are entitled, to a better performance."

A GNER spokesmansaid the service had improved, adding: "Under the industry measures, performance has got better." In the 12 months up to March, GNER says that using the charter measure 89.9 per cent of trains were on time - matching British Rail's performance.

The company is also planning to buy five new tilting trains to increase joinery times and will overhaul all rolling stock this summer to improve train reliability.

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in