From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.The opening of the domestic electricity market to competition has hit a further setback with another two regional suppliers warning they would not meet next April's deadline.
East Midlands Electricity and London Electricity have told the industry regulator, Offer, they may not be ready to launch competition in their areas until September of next year. This brings to three the number of suppliers having difficulties adapting their computer systems. The other company is Southern Electric.
News of the latest hold-up came as Offer published a report by its advisers, PA Consulting, warning the overall timetable for liberalisation remained tight and any late changes to the systems being introduced would result in significant delays.
The aim is to start allowing Britain's 22 million domestic electricity customers to shop around for supplies from next spring. The first four suppliers which expect to be ready are Eastern, Manweb, Seeboard and Yorkshire. However, the cost and complexity of installing the computer systems that will allow suppliers to talk with one another, new entrants and the electricity pool is causing increased worries.
A spokeswoman for Offer said that if detailed design requirements changed it could have a significant impact on the overall programme.
Professor Stephen Littlechild, the head of Offer, warned that with just over six months to go, much still remained to be done, although he welcomed the progress made so far.
Offer has written to East Midlands and London and asked what they are doing to bring themselves back on line.
Earlier this week Midlands Electricity confirmed it had abandoned a multi-million pound computer system after concluding that it would not be ready in time for next April.
The industry estimates the project will cost it pounds 850m but Professor Littlechild is only allowing it to pass pounds 500m of costs on to consumers.
-Michael Harrison