Maryland awards contract for Francis Scott Key Bridge rebuild after deadly collapse
Maryland transportation leaders have approved a contract for rebuilding the Francis Scott Key Bridge several months after it collapsed under the impact of a wayward container ship
Maryland awards contract for Francis Scott Key Bridge rebuild after deadly collapse
Show all 3Your support helps us to tell the story
From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.
At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.
The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.
Your support makes all the difference.Maryland transportation leaders on Thursday approved a contract for rebuilding the Francis Scott Key Bridge several months after the 1.6-mile (2.6-kilometer) steel span collapsed under the impact of a massive container ship that lost power and crashed into one of its supporting columns.
In the immediate aftermath of the deadly March 26 collapse, officials quickly promised to rebuild the bridge — a longstanding Baltimore landmark and vital piece of transportation infrastructure.
They cited a 2028 completion date and estimated the project would cost $1.7 billion and would include significantly more pier protection to better defend against future wayward ships.
At a monthly meeting Thursday morning, the Maryland Transportation Authority board awarded a $73 million contract for the first phase of the project to Kiewit Infrastructure, which calls itself “one of North America’s largest and most respected engineering and construction organizations.”
The company was founded in 1884 to provide masonry services in Omaha, Nebraska, according to its website. Its notable past projects include the Fort McHenry Tunnel under Baltimore’s harbor, which opened in 1985. More drivers have been using the tunnel since the bridge collapse eliminated one of three water crossings that allowed them to bypass downtown Baltimore.
Kiewit officials didn’t immediately respond to a request for comment Thursday morning.
In announcing their recommendation to the board, state transportation officials said the company’s proposal was ranked first for its technical contents despite being somewhat more expensive than others.
Officials said the project will advance in two phases, with the first focusing on the design work and other necessary steps before construction begins, which could include demolition of the remaining pieces of the bridge that are still standing. Phase one is expected to be completed within a year.
Kiewit will have “exclusive negotiating rights” for the second phase, transportation officials said in a statement following the board meeting. “In the event a guaranteed maximum price is not agreed upon, the MDTA will deliver the work under a separate contracting mechanism,” the statement read.
Officials have said the new bridge will be somewhat taller than the old one to accommodate ever-larger ships entering Baltimore’s harbor. The original Key Bridge took five years to construct and opened in 1977.
The March bridge collapse killed six members of a road work crew who were filling potholes on the bridge when it came crashing down into the water below. Baltimore’s busy port was closed for months after the collapse and increased traffic congestion in the region remains a problem for drivers.
An FBI investigation is ongoing into the circumstances leading up to the collapse, including power outages experienced by the cargo ship Dali while it was still docked in Baltimore.
The state transportation board also on Thursday approved a proposal to remit the proceeds from a recent $350 million insurance payout to the federal government. They called the decision a show of good faith as discussions continue about whether the federal government will cover 100% of the cleanup and rebuilding costs. Chubb, the company that insured the bridge, made the $350 million payout to the state, officials said this week.
Ongoing litigation will ultimately determine other assignments of liability in the bridge collapse, which could become one of the most expensive maritime disasters in U.S. history.
The federal government generally picks up 90% of the tab and the state 10% when replacing disaster-damaged interstate highways and bridges, but the Biden administration and members of Maryland’s congressional delegation are pushing congressional lawmakers to approve a 100% reimbursement.
Officials have said they expect that federal taxpayers will eventually be made whole for replacing the bridge through insurance payouts and damages, but that may take a while.
___
Associated Press writer Brian Witte contributed from Annapolis.
Subscribe to Independent Premium to bookmark this article
Want to bookmark your favourite articles and stories to read or reference later? Start your Independent Premium subscription today.