Stay up to date with notifications from The Independent

Notifications can be managed in browser preferences.

Auditors criticise Dome procedures

Fran Abrams
Tuesday 06 January 1998 19:02 EST
Comments

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

The company in charge of the Millennium Exhibition broke the rules when it let contracts for planning, marketing and sponsorship, according to an internal auditors' report.

KPMG found that in one case work had started before a legally binding contract was in place. In others, there was insufficient evidence that contracts had been let on a competitive basis or with clear specifications. Sir John Bourn, the Comptroller and Auditor General, has said in a report to Parliament that he finds the processes used "unsatisfactory".

The report, published at Westminster yesterday, relates to the period from October to December 1996, before the new government and the New Millennium Experience Company took over. It says that in the few months after Barry Hartop took over as chief executive of Millennium Central, the company in charge at the time, there were fears about the way contracts were being let.

KPMG were asked to look at the main 15 contracts, amounting to some pounds 500,000. The auditors found that only three followed the procurement procedures agreed with the Millennium Commission.

A separate report by the National Audit Office found that a number of payments made at around the same time were irregular, although not sufficiently serious to justify further action.

Eric Sorensen, the chief executive of the Millennium Commission, said the errors had mainly been technical ones of documentation, and he was confident that the problems had now been cleared up. "The report also makes clear there is no fraud or corruption and things were put right at the time," he said.

- Fran Abrams

Political Correspondent

Andrew Marr, page 19

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in