Stay up to date with notifications from The Independent

Notifications can be managed in browser preferences.

Supreme Court allows construction to resume on the Mountain Valley Pipeline

The Supreme Court is allowing construction to resume on a contested natural-gas pipeline that is being built through Virginia and West Virginia

Via AP news wire
Thursday 27 July 2023 11:10 EDT

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

The Supreme Court on Thursday allowed construction to resume on a contested natural-gas pipeline that is being built through Virginia and West Virginia.

Work on the Mountain Valley Pipeline had been blocked by the federal appeals court in Richmond, Virginia, even after Congress ordered the project's approval as part of the bipartisan bill to increase the debt ceiling. President Joe Biden signed the bill into law in June.

The high court's order came as a three-judge panel of the 4th U.S. Circuit Court of Appeals was hearing arguments in the case.

The Biden administration backed the company in calling for the Supreme Court's intervention.

Lawyers for the company said they needed quick Supreme Court action to keep plans on track to finish building the 300-mile (500-kilometer) pipeline and put it into service by the winter, when the need for natural gas for heating grows.

Environmental groups have opposed the the $6.6 billion project, designed to meet growing energy demands in the South and Mid-Atlantic by transporting gas from the Marcellus and Utica fields in Pennsylvania and Ohio.

Mountain Valley Pipeline said the work is largely complete, except for a 3-mile (5-kilometer) section that cuts through the Jefferson National Forest.

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in