Tribes, environmental groups ask US court to block $10B energy transmission project in Arizona

A federal judge is being asked to issue a stop-work order on a $10 billion electricity transmission line slated to run through a remote southeastern Arizona valley

Susan Montoya Bryan,Ken Ritter
Monday 22 January 2024 18:59 EST

Your support helps us to tell the story

From reproductive rights to climate change to Big Tech, The Independent is on the ground when the story is developing. Whether it's investigating the financials of Elon Musk's pro-Trump PAC or producing our latest documentary, 'The A Word', which shines a light on the American women fighting for reproductive rights, we know how important it is to parse out the facts from the messaging.

At such a critical moment in US history, we need reporters on the ground. Your donation allows us to keep sending journalists to speak to both sides of the story.

The Independent is trusted by Americans across the entire political spectrum. And unlike many other quality news outlets, we choose not to lock Americans out of our reporting and analysis with paywalls. We believe quality journalism should be available to everyone, paid for by those who can afford it.

Your support makes all the difference.

A federal judge is being asked to issue a stop-work order on a $10 billion transmission line being built through a remote southeastern Arizona valley to carry wind-powered electricity to customers as far away as California.

A 32-page lawsuit filed on Jan. 17 in U.S. District Court in Tucson, Arizona, accuses the U.S. Interior Department and Bureau of Land Management of refusing for nearly 15 years to recognize “overwhelming evidence of the cultural significance” of the remote San Pedro Valley to Native American tribes including the Tohono O’odham, Hopi, Zuni and Western Apache.

The suit was filed shortly after Pattern Energy received approval to transmit electricity generated by its SunZia Transmission wind farm in central New Mexico through the San Pedro Valley east of Tucson and north of Interstate 10.

The lawsuit calls the valley “one of the most intact, prehistoric and historical ... landscapes in southern Arizona,” and asks the court to issue restraining orders or permanent injunctions to halt construction.

“The San Pedro Valley will be irreparably harmed if construction proceeds,” it says.

SunZia Wind and Transmission and government representatives did not respond Monday to emailed messages. They are expected to respond in court. The project has been touted as the biggest U.S. electricity infrastructure undertaking since the Hoover Dam.

Plaintiffs in the lawsuit are the Tohono O’odham Nation, the San Carlos Apache Reservation and the nonprofit organizations Center for Biological Diversity and Archaeology Southwest.

“The case for protecting this landscape is clear,” Archaeology Southwest said in a statement that calls the San Pedro “Arizona’s last free-flowing river,” and the valley the embodiment of a "unique and timely story of social and ecological sustainability across more than 12,000 years of cultural and environmental change.”

The valley represents a 50-mile (80-kilometer) stretch of the planned 550-mile (885-kilometer) conduit expected to carry electricity linking massive new wind farms in central New Mexico with existing transmission lines in Arizona to serve populated areas as far away as California. The project has been called an important part of President Joe Biden's goal for a carbon pollution-free power sector by 2035.

Work started in September in New Mexico after negotiations that spanned years and resulted in the approval from the Bureau of Land Management, the federal agency with authority over vast parts of the U.S. West.

The route in New Mexico was modified after the U.S. Defense Department raised concerns about the effects of high-voltage lines on radar systems and military training operations.

Work halted briefly in November amid pleas by tribes to review environmental approvals for the San Pedro Valley, and resumed weeks later in what Tohono O’odham Chairman Verlon M. Jose characterized as "a punch to the gut.”

SunZia expects the transmission line to begin commercial service in 2026, carrying more than 3,500 megawatts of wind power to 3 million people. Project officials say they conducted surveys and worked with tribes over the years to identify cultural resources in the area.

A photo included in the court filing shows an aerial view in November of ridgetop access roads and tower sites being built west of the San Pedro River near Redrock Canyon. Tribal officials and environmentalists say the region is otherwise relatively untouched.

The transmission line also is being challenged before the Arizona Court of Appeals. The court is being asked to consider whether state regulatory officials there properly considered the benefits and consequences of the project.

____

Ritter reported from Las Vegas, Nevada.